Friday, November 13, 2015

Evidence driven Project Management competency improvement

In Large and medium organizations, the competency improvement needs are identified using a top down approach.  This approach  helps in taking the organization to the next set of competencies, based on the process/product/technology road maps and assessment of the current competencies.  The needs so identified  are addressed  through the competency improvement of the individual employee, while addressing his/her career preferences. While this is usually helpful as a first step and results in a set of trainings, this  may not help address the deficiencies fully.  I take project management as an example and present an approach for assessing the competency gaps and tailoring an improvement solution that can be driven by Project Management Office (PMO) or equivalent role.


As we know when a  software projects is challenged, root causes are identified and a solution to address the same is implemented. This is more likely to be adhoc and may fail to address  deficiencies holistically. PMOs can  follow the structured approach below as a better alternative.

1) In the recent review period( last month/quarter/year), identify the challenges faced  by each project,  assigning one or more of  the 22  anti patterns (examples: Detailitis plan, Road to Nowhere, Micro management) compiled and  analysed by Pedro Silva et.al, "Software Project Management Learning from Our Mistakes", IEEE Software, May/June 2015 pp 40-43.  This could be tailored as appropriate.

2) Perform a statistical analysis on the anti patterns to identify the top  anti patterns.

3) Identify the impacted roles and root causes.

4) Based on the above, identify the solution from one or more of the suggested solution types (process/role/technology/training).

5) Work with internal/external solution providers to implement the corrective actions spanning process redesign/training/coaching  etc.

6) Repeat the above steps to see whether  the solution  has yielded results.

In my extensive experience in industry, the first and last steps are  not given due importance with the result that the competency improvement remains weak at best. Do you agree? Share your views.

Monday, October 21, 2013

Supply and demand for Project Management skills in India

The recently released report by  KPMG-PMI on  Schedule and Cost overruns on Infrastructure projects in India  is interesting to read. The summary is that lack of qualified project manager and other engineering resources along with  external issues such as regulatory delays,  site handover, poor scope management are the major causes for Schedule overrun.   Poor resource,  procurement and scope  management are identified as some of  the major issues causing cost overrun.  As per the report, these  can be addressed easily  by improving the PM capability of the organization.
Credit:KPMG In India & PMG Study


Lack of skilled manpower, impacting schedule  is felt deeply in  Coal, Steel sectors followed by Power, Roads&Highways and then by Railways, Telecommunication. Scope creep, Design change, Environmental safety are major causes affecting cost overrun in Steel and Civil Aviation sectors. Telecom sector seemed did no have cost overrun.

86% of survey participants have  expressed the need for  PMOs to address the Schedule and Cost overruns and some have already established an internal PMO/engaged an external PMO. 56%  have reported use of Risk Management practices and  76% stated that their Risk management is effective.  Therefore, the conclusion that  poor risk  practice could be the reason,  based on the fact that 53% are behind schedule and 34% overspend seemed a bit surprising, though the report  covered various issues that impacted the project in the preceding chapters.

Taking the case of construction sector, the demand for project managers is estimated at 70,000 in 2010 moving to 2,27,500 by 2022.  Supply was projected to be 1,20,000 as per the twelfth five year plan. As the number of civil engineering seats have not grown well in the past(possibly due to the lure of CS/IT), it was recommended to introduce PM as a subject in Civil Engineering.

The report also provides a set of recommendations to expedite infrastructure projects. Three tier PMO (National,State, Implementation level) and setting up internal Project Academy in each organization as was done successfully by  IT industry are some of the recommendations. The report also had few case studies on how different organizations are dealing with the challenges. While the report looks good overall,  it could have been improved by use of visuals from Indian construction scene, rather than some stock photography of western country infrastructure projects. 

When I joined  engineering 29 years back, I opted for Electronics & Communication Engineering, which was least popular. I was glad that I  was able to land a government job through campus placements, when I finished the course. My civil engineering friends  had a hard time getting jobs. Some of them moved to Computer Science(CS)/Information Technology(IT) for their  post graduation course and  had made a good career subsequently.  Looks like what is required is the reverse now, as there is a glut of CS/IT engineers, many of whom could be easily trained for Project Management through short term bridge courses, which the report authors  seem to have missed.